When installing overhead line electrification (OLE) foundations one of the most challenging locations is a bridge. The majority of bridges have no original design specification, blue-prints or fabrication sheets. As a result, the client can be unaware where rebar is positioned without further investigation.

An OLE foundation requires four holes for the structure to be anchored to. If one of the four holes hits rebar, then the whole structure has to be repositioned. If rebar is continously being hit whilst drilling for anchor and cantilever positions then there can be significant increases in cost and time. The templates for OLE can be repositioned within 30 cm of the original proposed location along the track but are not allowed to go over the track.

Scope of work

Geo-Info were requested to scan a bridge's roof and sides to locate rebar using a non-invasive technique. The scope of work was for Geo-Info to:

Deliverables

Latest 'Blog Entries

54321 Challenge

Congratulations to Adrian for completing the 54321 Challenge in Ireland … Read More

Mala Easy Locator Training

Tomaz attended a two day training course with Mala this week … Read More

HEP Blockade Finishes

Blockade on Highland Enhance Programme between Aberdeen and Dyce comes to an end. … Read More

Our Clients and Suppliers